TGS Baltic successfully represented LTG Infra in a litigation case concerning construction delay in the Rail Baltica project

31.05.2021 TGS Baltic successfully represented LTG Infra in a litigation case concerning construction delay in the Rail Baltica project

We advised LTG Infra, a subsidiary of Lietuvos Geležinkeliai, the largest railway group in the Baltic States, in a dispute between LTG Infra and the consortium of the German capital Estonian company Leonhard Weiss RTE, Hidrostatyba and Autokausta over a delay in the implementation of EUR 54.8 million contract on railway construction from Kaunas to Palemonas, signed in June 2018.

The Kaunas Regional Court fully upheld the statement of claim of LTG Infra, according to which the consortium must pay a fine of EUR 0.5 million to LTG Infra.

The client was represented by associate partners Karolis Smaliukas, Žydrūnė Stuglytė, associates Jonas Jastremskas and Berta Kašėtaitė.